JBoss Fuse 6.1 now has a JBoss Fuse BOM (Bill of Materials), which defines the versions of all the JBoss Fuse Maven artifacts. You can use the BOM to simplify migration of your Maven POM files. Instead of updating the
version
elements on each Maven dependency, all you need to do is to import the latest JBoss Fuse BOM, which defines default versions for all of the dependencies provided by JBoss Fuse.
JBoss Fuse BOM
The JBoss Fuse BOM is a parent POM that defines the versions for all of the Maven artifacts provided by JBoss Fuse. The JBoss Fuse BOM exploits Maven's dependency management mechanism to specify default versions for the Maven artifacts, so that it is no longer necessary to specify the artifact versions explicitly in your POM.
Current version of the JBoss Fuse BOM
The easiest way to discover the current version of the JBoss Fuse BOM is to examine one of the sample
pom.xml
files from the quickstarts
examples. For example, in the InstallDir/quickstarts/eip/pom.xml
file, you can find a line that defines the JBoss Fuse BOM version, as follows:
<project ...> ... <properties> ... <!-- the version of the JBoss Fuse BOM, defining all the dependency versions --> <jboss.fuse.bom.version>6.2.0.redhat-133</jboss.fuse.bom.version> </properties> ... </project>
How to migrate Maven dependencies using the JBoss Fuse BOM
To migrate Maven dependencies using the JBoss Fuse BOM, open the Maven
pom.xml
file for your project and edit it as follows:
- Define the JBoss Fuse BOM version as a property in your
pom.xml
file, using the current BOM version. For example:<project ...> ... <properties> ... <jboss.fuse.bom.version>6.2.0.redhat-133</jboss.fuse.bom.version> </properties> ... </project>
- Reference the JBoss Fuse BOM parent POM in a
dependencyManagement
element, so that it defines default versions for the artifacts provided by JBoss Fuse. Add the followingdependencyManagement
element to yourpom.xml
file:<project ...> ... <dependencyManagement> <dependencies> <dependency> <groupId>org.jboss.fuse.bom</groupId> <artifactId>jboss-fuse-parent</artifactId> <version>${jboss.fuse.bom.version}</version> <type>pom</type> <scope>import</scope> </dependency> </dependencies> </dependencyManagement> ... </project>
- Now delete all of the
version
elements in your JBoss Fuse dependencies. All of the versions defined in the JBoss Fuse BOM will be applied automatically to your dependencies (through the Maven dependency management mechanism). For example, if you already had some Apache Camel dependencies, as follows:<dependencies> <dependency> <groupId>org.apache.camel</groupId> <artifactId>camel-core</artifactId> <version>2.15.1.redhat-620133</version> </dependency> <dependency> <groupId>org.apache.camel</groupId> <artifactId>camel-blueprint</artifactId> <version>2.15.1.redhat-620133</version> </dependency> <dependency> <groupId>org.apache.camel</groupId> <artifactId>camel-jetty</artifactId> <version>2.15.1.redhat-620133</version> </dependency> ... </dependencies>
You would delete the version elements, so that the dependencies are specified as follows:<dependencies> <dependency> <groupId>org.apache.camel</groupId> <artifactId>camel-core</artifactId> </dependency> <dependency> <groupId>org.apache.camel</groupId> <artifactId>camel-blueprint</artifactId> </dependency> <dependency> <groupId>org.apache.camel</groupId> <artifactId>camel-jetty</artifactId> </dependency> ... </dependencies>
- In future, when you migrate to a later version of JBoss Fuse, all that you need to do to upgrade your
pom.xml
file is to edit thejboss.fuse.bom.version
property, so that it references the new version of the JBoss Fuse BOM.