Chapter 2. Migration planning


Select the migration approach that best aligns with your architecture, and customize the steps for your infrastructure.

Expand
FeatureMinimal downtime migrationMaintenance window migration

Primary Method

Parallel environments with reverse proxy or load balancer routing

Sequential process

Complexity

High: Requires configuration for dual-routing and traffic management.

Low: Straightforward, linear execution steps.

Read Downtime

10-30 seconds (Switchover latency)

1-2 hours (Full duration of maintenance)

Write Downtime

30-45 minutes (Final sync and import phase)

1-2 hours (Full duration of maintenance)

Infrastructure

Requires Nginx or HAProxy and running dual instances.

Single target environment.

Best For

High-availability production environments.

Development, staging, or systems with flexible SLAs.

Regardless of the migration path you choose, you need to:

  • Test the data migration in a staging environment before migrating production. A dry run helps you estimate timing for export and import phases. See Migrating Apicurio Registry data.
  • Verify client applications connect to Apicurio Registry 3.x after the data migration completes. For minimal downtime migrations, verify the load balancer routes to 3.x and update any clients that bypass the load balancer. For maintenance window migrations, update client configurations directly. See Migrating Apicurio Registry client applications.
  • Update configuration properties for the v3 deployment. Combine this with client updates where possible. See Updating Apicurio Registry configuration.

Minimal downtime migration

The objective is to keep the service reachable. While data is being moved, a reverse proxy (such as nginx) manages the cutover. See Migrating with minimal downtime.

Maintenance window migration

This approach ensures the cleanest data integrity. By stopping all client applications first, you ensure no data is in flight during the move. See Migrating in a maintenance window.

During a minimal downtime migration, you temporarily run both Apicurio Registry 2.6 and Apicurio Registry 3.x simultaneously. Plan for:

Infrastructure:

  • Separate database instances for v2 and v3 (or different schemas in the same database)
  • For KafkaSQL deployments: same Kafka cluster with different topic names
  • Load balancer capacity for routing traffic
  • Network connectivity between all components

Storage requirements:

  • v2 database/storage: existing size
  • v3 database/storage: approximately same size as v2 (plan for 110% of the v2 size)
  • Export file storage: approximately 10-20% of the database size (compressed)

Timeline:

  • Keep v2 running for 1-7 days after migration for rollback capability
  • Total parallel operation period: 1-7 days
  • Budget for staging environment testing before production migration

Prerequisites

Before beginning migration:

Expand
RequirementDescription

Staging environment

Test complete migration workflow before production

Load balancer

nginx, HAProxy, or similar for traffic management

Administrative access

Admin role credentials for export/import API endpoints and testing admin functionality

Database or storage

Separate database instance or schema (or separate Kafka topic) for Apicurio Registry 3.x

Backup

Current backup of 2.6 data

Rollback plan

Documented procedure to revert to v2 if needed

Red Hat logoGithubredditYoutubeTwitter

자세한 정보

평가판, 구매 및 판매

커뮤니티

Red Hat 문서 정보

Red Hat을 사용하는 고객은 신뢰할 수 있는 콘텐츠가 포함된 제품과 서비스를 통해 혁신하고 목표를 달성할 수 있습니다. 최신 업데이트를 확인하세요.

보다 포괄적 수용을 위한 오픈 소스 용어 교체

Red Hat은 코드, 문서, 웹 속성에서 문제가 있는 언어를 교체하기 위해 최선을 다하고 있습니다. 자세한 내용은 다음을 참조하세요.Red Hat 블로그.

Red Hat 소개

Red Hat은 기업이 핵심 데이터 센터에서 네트워크 에지에 이르기까지 플랫폼과 환경 전반에서 더 쉽게 작업할 수 있도록 강화된 솔루션을 제공합니다.

Theme

© 2026 Red Hat
맨 위로 이동