Chapter 20. Managing Resource Usage


When Red Hat Gluster Storage is deployed on the same machine as other resource intensive software and services, it can be useful to limit the resources that glusterd attempts to use in order to avoid resource contention between processes.
On Red Hat Gluster Storage 3.2 and higher deployments based on Red Hat Enterprise Linux 7, this can be configured using gdeploy. For more information, see Section 5.1.11, “Limiting Gluster Resources”.
On earlier versions of Red Hat Gluster Storage, it is necessary to manually configure a control group slice for the glusterd service in order to manage glusterd's access to system resources.

Procedure 20.1. Limiting glusterd resources on RHEL7 based Red Hat Gluster Storage

  1. Stop all gluster processes

    # systemctl stop glusterd
    Copy to Clipboard Toggle word wrap

    Important

    If glusterd crashes, there is no functionality impact to this crash as it occurs during the shutdown. For more information, see Section 24.3, “Resolving glusterd Crash”
  2. Create a service configuration directory for glusterd

    # mkdir /etc/systemd/system/glusterd.service.d
    Copy to Clipboard Toggle word wrap
  3. Create a service configuration file

    # echo "[Service]
    CPUAccounting=yes
    Slice=glusterfs.slice" >> /etc/systemd/system/glusterd.service.d/99-cpu.conf
    Copy to Clipboard Toggle word wrap
  4. Create a slice file

    The following defines a slice that sets CPUQuota to the recommended value of 400% (four cores).
    # echo "[Slice]
    CPUQuota=400%" >> /etc/systemd/system/glusterfs.slice
    Copy to Clipboard Toggle word wrap
    You can alter the percentage to suit your environment by editing the value in the slice file:
    # systemctl set-property glusterfs.slice CPUQuota=value
    Copy to Clipboard Toggle word wrap
  5. Restart the system daemon

    # systemctl daemon-reload
    Copy to Clipboard Toggle word wrap
  6. Start gluster processes

    # systemctl start glusterd
    Copy to Clipboard Toggle word wrap
For more information about configuring resource management on Red Hat Enterprise Linux 7, see the Resource Management Guide: https://access.redhat.com/documentation/en-US/Red_Hat_Enterprise_Linux/7/html-single/Resource_Management_Guide/index.html#sec-What_are_Control_Groups
Resource management works differently on Red Hat Enterprise Linux 6. See the Red Hat Enterprise Linux 6 Resource Management Guide for details: https://access.redhat.com/documentation/en-US/Red_Hat_Enterprise_Linux/6/html/Resource_Management_Guide/ch-Using_Control_Groups.html
返回顶部
Red Hat logoGithubredditYoutubeTwitter

学习

尝试、购买和销售

社区

关于红帽文档

通过我们的产品和服务,以及可以信赖的内容,帮助红帽用户创新并实现他们的目标。 了解我们当前的更新.

让开源更具包容性

红帽致力于替换我们的代码、文档和 Web 属性中存在问题的语言。欲了解更多详情,请参阅红帽博客.

關於紅帽

我们提供强化的解决方案,使企业能够更轻松地跨平台和环境(从核心数据中心到网络边缘)工作。

Theme

© 2025 Red Hat