Prepare your hardware certification test plan
A hardware certification engineer creates a test plan by following these steps:
- Define the model by its specification.
- Determine the option.
- Remove unsupported operating system features and unintentional hardware.
- Apply the minimum test set criteria.
- Add the install, boot, and kdump requirements.
- Add additional policy requirements.
After performing the steps above, the items remaining determine the test plan for your hardware. The Hardware Catalog records the test plan under the Test Plan Progress.
Red Hat Hardware Certification Test Plans are not meant to substitute for proper and complete internal quality assurance testing, criteria, and processes. Each vendor is responsible for their own internal shipment criteria and is encouraged to do testing in excess of the required certification test plan items.